A board decides in March to close a plant but tells no one before year end. Then:
AA full provision
BA contingent asset
CAn accrual raised
DNo obligation yet
Answer & Solution
Correct answer: D. No obligation yet
A decision not communicated to those affected before year end raises no valid expectation, so no constructive obligation exists.
Keep practising AS 29 Provisions and Contingencies
Browse all AS 29 Provisions and Contingencies questions for CA Inter, or explore more Accounting topics.
Related questions
Use of estimates in preparing a provision:A present obligation where outflow is not probable is classed as a:To whom can an obligation be owed?Which obligation exists independently of the entity's future actions?A restructuring plan creates an obligation only if it is meant to:Which is evidence that a restructuring plan has started to be implemented?An executory contract falls within the provisions rules only if it is:Depreciation and doubtful debt provisions are really: