Projects: Rs 1,00,000 giving Rs 1,32,000, and Rs 10,000 giving Rs 13,750, both in a year at 10%. Higher NPV?
AThe Rs 10,000 one
BThe Rs 1,00,000 one
CBoth the same
DNeither of them
Answer & Solution
Correct answer: B. The Rs 1,00,000 one
NPVs are Rs 20,000 for the larger project against Rs 2,500 for the smaller, though the smaller has the higher IRR.
Keep practising Capital Budgeting
Browse all Capital Budgeting questions for CA Final, or explore more Strategicfinancialmanagement topics.
Related questions
R&D managers can use real options valuation to handle uncertainty whenA benefit of NPV for a firm with several projects is that NPVs areNPV accuracy relies heavily on the chosenSensitivity analysis studies how uncertainty in a model's output relates to itsAdjusted present value equals equity-financed NPV plus theA Rs 50,000 cash flow in a year has 60% probability; discount rate 10%. Risk-adjusted PV irNPV is the standard valuation method in which industry?Risk-adjusted NPV multiplies each cash flow by the