A project costs Rs 20,000 and gives Rs 8,000 yearly for 3 years. At 10% (annuity factor 2.4869) its NPV is about
ARs 4,000
BRs 105
CRs -105
DRs -4,000
Answer & Solution
Correct answer: C. Rs -105
8,000 x 2.4869 = 19,895, which is below 20,000, so NPV is about Rs -105 and the project is rejected.
Keep practising Capital Budgeting
Browse all Capital Budgeting questions for CA Final, or explore more Strategicfinancialmanagement topics.
Related questions
R&D managers can use real options valuation to handle uncertainty whenA benefit of NPV for a firm with several projects is that NPVs areNPV accuracy relies heavily on the chosenSensitivity analysis studies how uncertainty in a model's output relates to itsAdjusted present value equals equity-financed NPV plus theA Rs 50,000 cash flow in a year has 60% probability; discount rate 10%. Risk-adjusted PV irNPV is the standard valuation method in which industry?Risk-adjusted NPV multiplies each cash flow by the