A project costs Rs 5,000 and returns Rs 3,000 at the end of each of two years. At 10% its NPV is about
ARs 1,000
BRs 500
CRs 207
DRs -207
Answer & Solution
Correct answer: C. Rs 207
3,000 x 1.7355 = 5,206.5; minus 5,000 gives about Rs 207.
Keep practising Capital Budgeting
Browse all Capital Budgeting questions for CA Final, or explore more Strategicfinancialmanagement topics.
Related questions
R&D managers can use real options valuation to handle uncertainty whenA benefit of NPV for a firm with several projects is that NPVs areNPV accuracy relies heavily on the chosenSensitivity analysis studies how uncertainty in a model's output relates to itsAdjusted present value equals equity-financed NPV plus theA Rs 50,000 cash flow in a year has 60% probability; discount rate 10%. Risk-adjusted PV irNPV is the standard valuation method in which industry?Risk-adjusted NPV multiplies each cash flow by the