A project with larger outlay but lower IRR has a higher NPV. With no capital limit, which is chosen?
AHigher IRR
BHigher NPV
CLower outlay
DShorter payback
Answer & Solution
Correct answer: B. Higher NPV
NPV measures the increase in shareholder wealth, so the higher NPV is preferred when maximising value.
Keep practising Capital Budgeting
Browse all Capital Budgeting questions for CA Final, or explore more Strategicfinancialmanagement topics.
Related questions
R&D managers can use real options valuation to handle uncertainty whenA benefit of NPV for a firm with several projects is that NPVs areNPV accuracy relies heavily on the chosenSensitivity analysis studies how uncertainty in a model's output relates to itsAdjusted present value equals equity-financed NPV plus theA Rs 50,000 cash flow in a year has 60% probability; discount rate 10%. Risk-adjusted PV irNPV is the standard valuation method in which industry?Risk-adjusted NPV multiplies each cash flow by the