IRR calculation excludes external factors such as the
Ainitial outlay
Btiming of inflows
Cproject cash flows
Dcost of capital
Answer & Solution
Correct answer: D. cost of capital
IRR is derived only from the project's own cash flows; the cost of capital is used only afterwards for comparison.
Keep practising Capital Budgeting
Browse all Capital Budgeting questions for CA Final, or explore more Strategicfinancialmanagement topics.
Related questions
R&D managers can use real options valuation to handle uncertainty whenA benefit of NPV for a firm with several projects is that NPVs areNPV accuracy relies heavily on the chosenSensitivity analysis studies how uncertainty in a model's output relates to itsAdjusted present value equals equity-financed NPV plus theA Rs 50,000 cash flow in a year has 60% probability; discount rate 10%. Risk-adjusted PV irNPV is the standard valuation method in which industry?Risk-adjusted NPV multiplies each cash flow by the