A plant with expansion capacity costs Rs 12 crore against Rs 10 crore for one without. The option premium is
ARs 2 crore
BRs 12 crore
CRs 10 crore
DRs 22 crore
Answer & Solution
Correct answer: A. Rs 2 crore
The extra Rs 2 crore spent for the possibility of expansion is the premium paid for the option.
Keep practising Capital Budgeting
Browse all Capital Budgeting questions for CA Final, or explore more Strategicfinancialmanagement topics.
Related questions
R&D managers can use real options valuation to handle uncertainty whenA benefit of NPV for a firm with several projects is that NPVs areNPV accuracy relies heavily on the chosenSensitivity analysis studies how uncertainty in a model's output relates to itsAdjusted present value equals equity-financed NPV plus theA Rs 50,000 cash flow in a year has 60% probability; discount rate 10%. Risk-adjusted PV irNPV is the standard valuation method in which industry?Risk-adjusted NPV multiplies each cash flow by the