MIRR was designed to fix which weakness of IRR?
AIgnoring time value of money
BUsing accounting profits
CIgnoring the project's size
DReinvestment assumed at the IRR
Answer & Solution
Correct answer: D. Reinvestment assumed at the IRR
IRR implicitly lets interim inflows earn the project's own IRR, while MIRR reinvests them at a second, more realistic rate.
Keep practising Capital Budgeting
Browse all Capital Budgeting questions for CA Final, or explore more Strategicfinancialmanagement topics.
Related questions
R&D managers can use real options valuation to handle uncertainty whenA benefit of NPV for a firm with several projects is that NPVs areNPV accuracy relies heavily on the chosenSensitivity analysis studies how uncertainty in a model's output relates to itsAdjusted present value equals equity-financed NPV plus theA Rs 50,000 cash flow in a year has 60% probability; discount rate 10%. Risk-adjusted PV irNPV is the standard valuation method in which industry?Risk-adjusted NPV multiplies each cash flow by the