MIRR was designed to fix which weakness of IRR?

AIgnoring time value of money
BUsing accounting profits
CIgnoring the project's size
DReinvestment assumed at the IRR
Answer & Solution
Correct answer: D. Reinvestment assumed at the IRR
IRR implicitly lets interim inflows earn the project's own IRR, while MIRR reinvests them at a second, more realistic rate.