Under the completed-contract method, a firm with one project shows what until the final year?
AFull profit on the job
BNil revenue and nil cost
CHalf of the revenue
DOnly the cost incurred
Answer & Solution
Correct answer: B. Nil revenue and nil cost
Revenue, cost and gross profit are held back until the project is fully complete.
Keep practising Ind AS 115 Revenue from Contracts with Customers
Browse all Ind AS 115 Revenue from Contracts with Customers questions for CA Final, or explore more Financialreporting topics.
Related questions
Repayment of debt principal belongs to which activity?In the indirect method, an increase in an asset account is treated how?The indirect method of cash flow preparation starts from what?Purchase or sale of an asset is classified under which activity?Under IAS 7, where may interest paid be reported?Which item does a cash flow statement exclude as a non-cash transaction?Why can a profitable company still run short of cash?A cash flow statement splits cash flows into which three?