After ranking, the highest ranked projects are implemented until when?

AThe capital budget is used up
BThe tax year comes to an end
CThe first loss is reported
DEvery project is accepted
Answer & Solution
Correct answer: A. The capital budget is used up
Ranking is used because capital is limited, so projects are taken in order until the budget runs out.