Under the chain method, a 3 year and a 4 year project are compared over how many years?

A24 years
B10 years
C12 years
D7 years
Answer & Solution
Correct answer: C. 12 years
Four repetitions of the 3 year project and three repetitions of the 4 year project each span 12 years.