With no capital limit and independent projects, which are accepted?
AOnly the shortest payback project
BOnly the largest project
COnly the highest IRR project
DAll projects with positive NPV
Answer & Solution
Correct answer: D. All projects with positive NPV
Without capital constraints or dependencies, every project with a positive NPV adds value, so all are accepted.
Keep practising Capital Budgeting
Browse all Capital Budgeting questions for CA Inter, or explore more Financial Management topics.
Related questions
Under which cash flow statement section is capex commonly reported?Which spending is capital expenditure as it extends asset life?Which of these spending items is a capital expenditure?Where do capitalised expenditures show up in the financial statements?Which expense is the counterpart of capital expenditure?What is capital expenditure (capex)?Payback also ignores which part of a project's cash flows?Which key weakness does the simple payback period have?