A project has a PI of 1.05 on an outlay of Rs 4,00,000. What is its NPV?
ARs 20,000
BRs 40,000
CRs 5,000
DRs 4,20,000
Answer & Solution
Correct answer: A. Rs 20,000
NPV = (1.05 minus 1) x 400,000 = Rs 20,000.
Keep practising Profitability Index
Browse all Profitability Index questions for CA Inter, or explore more Financial Management topics.
Related questions
Which rule applies to a PI result of 1.092 for an independent project?Perpetual inflow of Rs 12,000 a year at 10 percent against an outlay of Rs 1,00,000 gives Which of these is a technique that ignores the time value of money?A project has NPV zero at 18 percent discount rate. What is its IRR?If IRR exceeds the cost of capital on a conventional project, what is NPV?Which discount rate is often used when discounting project cash flows in NPV?Why is NPV on after-interest cash flows wrong?What is a limitation of the NPV approach regarding non-financial matters?