Two projects have ARR of 14% and 18% and similar risk. Which is preferred?
AThe 14% project
BThe 18% project
CBoth equally
DNeither one
Answer & Solution
Correct answer: B. The 18% project
The project with the higher ARR is more attractive when projects are compared.
Keep practising Accounting Rate of Return
Browse all Accounting Rate of Return questions for CA Inter, or explore more Financial Management topics.
Related questions
Which measures do economists prefer over payback for return?Rs 9,00,000 is invested and net cash flow is Rs 1,80,000 a year. Payback?A: profit Rs 40,000 on average investment Rs 2,00,000. B: Rs 54,000 on Rs 3,60,000. HigherCost Rs 12,00,000 and scrap Rs 2,00,000. Average investment under ARR?Cost Rs 3,00,000, scrap Rs 60,000, 4 years, total profit Rs 1,44,000. ARR?Which goal underlies capital budgeting in corporate finance?Capital budgeting mainly concerns which type of spending?Companies create value when their return on capital is above what?