Two projects have ARR of 14% and 18% and similar risk. Which is preferred?

AThe 14% project
BThe 18% project
CBoth equally
DNeither one
Answer & Solution
Correct answer: B. The 18% project
The project with the higher ARR is more attractive when projects are compared.