ARR is 15% and the required rate is 12%. What is the decision?
AReject the project
BDefer for a year
CGather more data
DAccept the project
Answer & Solution
Correct answer: D. Accept the project
The ARR exceeds the required rate, so the project clears the acceptance rule.
Keep practising Accounting Rate of Return
Browse all Accounting Rate of Return questions for CA Inter, or explore more Financial Management topics.
Related questions
Which measures do economists prefer over payback for return?Rs 9,00,000 is invested and net cash flow is Rs 1,80,000 a year. Payback?A: profit Rs 40,000 on average investment Rs 2,00,000. B: Rs 54,000 on Rs 3,60,000. HigherCost Rs 12,00,000 and scrap Rs 2,00,000. Average investment under ARR?Cost Rs 3,00,000, scrap Rs 60,000, 4 years, total profit Rs 1,44,000. ARR?Which goal underlies capital budgeting in corporate finance?Capital budgeting mainly concerns which type of spending?Companies create value when their return on capital is above what?