ARR is 15% and the required rate is 12%. What is the decision?

AReject the project
BDefer for a year
CGather more data
DAccept the project
Answer & Solution
Correct answer: D. Accept the project
The ARR exceeds the required rate, so the project clears the acceptance rule.