Comparing one project's IRR with the required rate, in isolation, is equivalent to:
Athe NPV decision rule
Bthe payback method
Cthe ratio analysis rule
Dthe book return method
Answer & Solution
Correct answer: A. the NPV decision rule
For a lone conventional project, IRR above the required rate and positive NPV give the same accept decision.
Keep practising Internal Rate of Return
Browse all Internal Rate of Return questions for CA Inter, or explore more Financial Management topics.
Related questions
The same return received later gives an IRR that is:If cash flows are random variables, as in a life annuity, IRR uses their:The AIRR approach of Magni was introduced to solve problems of:In personal finance the IRR measures what type of performance?With no capital constraint, which projects does a firm accept to maximize value?Mutually exclusive projects are those from which:The equivalent annuity method divides the NPV by what to annualize it?The equivalent annuity method is often used to compare projects of: