The chain method compares 4 repeats of a 3-year project with what?

A12 repeats of the 4-year one
B4 repeats of the 4-year one
C3 repeats of the 4-year one
D2 repeats of the 4-year one
Answer & Solution
Correct answer: C. 3 repeats of the 4-year one
Both chains must span 12 years, since 4 times 3 equals 3 times 4.