The cost to replace existing assets at present prices is the
ADifferential cost
BReplacement cost
COpportunity cost
DHistorical cost
Answer & Solution
Correct answer: B. Replacement cost
The cost at which existing materials or fixed assets could be replaced now is the replacement cost.
Keep practising Direct Costs
Browse all Direct Costs questions for CA Inter, or explore more Cost and Management Accounting topics.
Related questions
Materials 30,000, labour 18,000, royalty 6,000, head office rent 9,000. Direct cost?Royalty is Rs 3 per unit on 4,000 units. Direct expenses amount toA machine costing 12 is improved at 20 and sold for 45. What is the profit?Two units cost Rs 10 each and two cost Rs 12 each. Two are sold; FIFO cost?Factory burden means overhead incurred at theOverhead per labour hour added to labour cost is aA gap between actual and standard material or labour cost is recorded asCOGS includes raw material costs together with