Direct project costs are usually charged to projects

AOn an item-by-item basis
BOn a lump-sum basis
COn an annual average
DOn a pooled basis
Answer & Solution
Correct answer: A. On an item-by-item basis
Because they are easily traced, each direct item is charged individually to the project.