In construction, direct costs are materials, labour and

AEquipment used on the job
BCorporate advertising
CHead office rent bills
DStatutory auditor fees
Answer & Solution
Correct answer: A. Equipment used on the job
Equipment deployed on the job is directly involved in the cost object, so it is a direct cost.