Start learning →

Budgeted material cost was Rs 50,000 and actual cost Rs 54,000. What is the variance?

ARs 4,000 adverse
BRs 50,000 adverse
CRs 54,000 favourable
DRs 4,000 favourable
Answer & Solution
Correct answer: A. Rs 4,000 adverse
Actual cost exceeded budget by 4,000, which is worse than expected, so the variance is adverse.
Practise this question with Quill — CA Inter →

Keep practising Budgets and Budgetary Control

Browse all Budgets and Budgetary Control questions for CA Inter, or explore more Cost and Management Accounting topics.

Start a Budgets and Budgetary Control lesson →
Related questions