A material is used at 80 units a day with a 12 day lead time. Reorder level without safety stock?

A800 units
B1,200 units
C960 units
D1,040 units
Answer & Solution
Correct answer: C. 960 units
Daily usage of 80 times 12 days of lead time equals 960 units.