Overhead is budgeted at Rs 100 per labour hour. A job takes 10 hours by a worker paid Rs 25 per hour. Overhead charged?

ARs 2,500
BRs 1,000
CRs 1,250
DRs 250
Answer & Solution
Correct answer: B. Rs 1,000
The rate is per hour, so overhead is 10 x 100 = 1,000 regardless of the actual wage rate paid.