Physical output A 600 units, B 400 units, joint cost Rs 60,000. B is charged

ARs 24,000
BRs 20,000
CRs 36,000
DRs 30,000
Answer & Solution
Correct answer: A. Rs 24,000
Joint cost per unit is 60,000 over 1,000, i.e. Rs 60; B's 400 units take Rs 24,000.