Wage cost variance is analysed into a rate component and which other component?

AUsage variance
BSpending variance
CEfficiency variance
DVolume variance
Answer & Solution
Correct answer: C. Efficiency variance
Labour variance separates the pay-rate difference from the difference in hours worked, which is the efficiency variance.