A cost fails the asset test at year end. At an interim date?

ATreated as deferred asset
BCapitalised until year end
CAlso fails, so expensed
DSpread over quarters
Answer & Solution
Correct answer: C. Also fails, so expensed
The same future economic benefit tests apply at interim dates as at year end.