If a change cannot be told apart as policy or estimate, it is treated as

AA change in policy
BA change in estimate
CA prior period item
DAn extraordinary item
Answer & Solution
Correct answer: B. A change in estimate
AS 5 resolves the doubt by treating the change as an estimate change, with appropriate disclosure.