Planning an audit is best described as:

Athe final step of the audit
Bthe client's responsibility
Ca one-time act at year-end
Da continual and iterative process, not a discrete phase
Answer & Solution
Correct answer: D. a continual and iterative process, not a discrete phase
Planning is continual and iterative, not a discrete phase.