In which entry mode does an independent contractor prepare the plant and hand it over ready to run?
ATurnkey project
BJoint venture
CFranchising
DLicensing
Answer & Solution
Correct answer: A. Turnkey project
A turnkey contractor oversees all preparation and turns the plant over fully ready for operation.
Related questions
Which is one of two macro factors driving globalization?Two firms pooling resources to form a separate jointly owned entity create what?What is the business practice of licensing a business model to another company?Compared with domestic trade, international trade is typically what?The exchange of capital, goods and services across borders is called what?What are documents called that do not comply with the terms of a letter of credit?Which payment tool gives an exporter a guarantee from a creditworthy bank?Mercantilists believed that accumulating what made a country wealthier?