Two equally risky projects return 10 per cent and 12 per cent. Which is normally chosen?

AThe 10 per cent one
BThe 12 per cent one
CBoth equally good
DNeither of them
Answer & Solution
Correct answer: B. The 12 per cent one
With equal risk, the project with the higher rate of return is preferred.