If A finishes a job in 12 days and B in 6 days, together:
- 9 days
- 3 days
- 6 days
- 4 days
Show answer and solution
Correct answer: D. 4 days
1. Rates: 1/12 + 1/6 = 3/12 = 1/4. 2. Time = 4 days.
_Source: 501-GMAT-Questions Section 4 / Manhattan Quant Bank_