Promoters qualify for the inter se transfer exemption if named as promoters for at least how long?Read the answer and worked solution →After a buy-back lifts a holder over the threshold, holding must fall below it within what?Read the answer and worked solution →Certain exempt acquisitions must be notified to exchanges at least how long beforehand?Read the answer and worked solution →The detailed public statement follows the public announcement within how many working days?Read the answer and worked solution →Under Regulation 14(1), the public announcement is sent to whom first?Read the answer and worked solution →A copy of the announcement goes to SEBI and the target within what time (Reg 14(2))?Read the answer and worked solution →The detailed public statement appears in an English daily, a Hindi daily and what else?Read the answer and worked solution →SEBI comments on the draft letter of offer within how many working days?Read the answer and worked solution →Offer consideration for fee purposes assumes what level of acceptance?Read the answer and worked solution →The escrow account must be created not later than when before the DPS?Read the answer and worked solution →Escrow on the first five hundred crore of consideration is what share of it?Read the answer and worked solution →A conditional offer's escrow is 100 per cent of minimum-acceptance sum or what share of total?Read the answer and worked solution →The tendering period in an open offer remains open for how many working days?Read the answer and worked solution →Payment to accepting shareholders is due within what time of the tendering period's end?Read the answer and worked solution →Delayed payment to accepting shareholders attracts interest at what annual rate?Read the answer and worked solution →A post-offer advertisement is due within how many working days after the offer period?Read the answer and worked solution →A competing offer must come within how many working days of the first DPS?Read the answer and worked solution →Competing offers follow which timeline under Regulation 20(8)?Read the answer and worked solution →Rival acquirers may raise price until how long before tendering starts?Read the answer and worked solution →Unclaimed escrow balances go to the Investor Protection and Education Fund after how long?Read the answer and worked solution →Acting on the agreement is allowed after how many working days from DPS with full cash escrow?Read the answer and worked solution →Acquisitions under the agreement must be completed within how long of the offer period's end?Read the answer and worked solution →Which event lets an open offer be withdrawn under Regulation 23(1)?Read the answer and worked solution →A withdrawal of an open offer must be announced within what time?Read the answer and worked solution →During an offer, material asset sales outside business need what, by postal ballot?Read the answer and worked solution →The target must furnish the shareholder list within how long of the identified date?Read the answer and worked solution →Who gives reasoned recommendations on the open offer for the target's shareholders?Read the answer and worked solution →Recommendations of the independent committee are published how long before tendering starts?Read the answer and worked solution →Disclosures of acquisitions under Regulation 29 go to exchanges within what time?Read the answer and worked solution →Regulation 29(2): holders of 5 per cent must report a change exceeding what?Read the answer and worked solution →

Worked practice questions

Promoters qualify for the inter se transfer exemption if named as promoters for at least how long?

  1. One year
  2. Two years
  3. Three years
  4. Five years
Show answer and solution

Correct answer: C. Three years

Regulation 10(1)(a)(ii) requires being named as promoters in filings for not less than three years before the proposed acquisition.

Open this question →

After a buy-back lifts a holder over the threshold, holding must fall below it within what?

  1. 30 days
  2. 60 days
  3. 90 days
  4. 180 days
Show answer and solution

Correct answer: C. 90 days

Regulation 10(3) exempts the increase if the shareholder cuts voting rights below the Regulation 3(1) threshold within ninety days of the buy-back closure.

Open this question →

Certain exempt acquisitions must be notified to exchanges at least how long beforehand?

  1. One working day
  2. Two working days
  3. Three working days
  4. Four working days
Show answer and solution

Correct answer: D. Four working days

Regulation 10(5) requires intimation of the proposed acquisition to the stock exchanges at least four working days beforehand.

Open this question →

How to practise

  1. Choose a SEBI Takeover and Insider Trading Regulations question and try to work out your answer.
  2. Open the question to check the correct answer and read its worked solution.
  3. Continue in the app for bite-sized lessons, explanations and review with Quill. You can start without creating an account.

More Law topics