Activity-Based Costing questions and exercises with answers

Showing questions 1–6 of 6.

Worked practice questions

Match each activity to its driver

Read exercise and reference answers
Matching pairs
  1. Left
    Production setup
    Right
    Number of setups
  2. Left
    Quality control
    Right
    Number of inspections
  3. Left
    Materials handling
    Right
    Number of material moves
  4. Left
    Electric power
    Right
    Kilowatt hours used
  5. Left
    Payroll
    Right
    Number of payroll checks processed
  6. Left
    Human resources
    Right
    Number of employees
Instructions
Tap an activity, then tap the count that measures how often it happens.
_Source: Jonick, Principles of Managerial Accounting, section 4.4 Activity-Based Costing for a Manufacturing Business_

Open this exercise →

Flip to match each activity rate

Read exercise and reference answers
Matching pairs
  1. A
    Setups
    B
    $50 per setup
  2. A
    Moves
    B
    $15 per move
  3. A
    Inspections
    B
    $25 per inspection
  4. A
    Clean-ups
    B
    $10 per cleanup
  5. A
    Cutting
    B
    $30 per machine hr
  6. A
    Assembly
    B
    $15 per labor hour
Instructions
Flip two cards to pair an activity with the rate charged each time it happens.
_Source: Jonick, Principles of Managerial Accounting, section 4.4 Activity-Based Costing for a Manufacturing Business_

Open this exercise →

Sort costs by how they get a rate

Read exercise and reference answers
Left
Traced activity
Items
  1. Item
    Setups
    Answer
    Traced activity
  2. Item
    Material moves
    Answer
    Traced activity
  3. Item
    Inspections
    Answer
    Traced activity
  4. Item
    Clean-ups
    Answer
    Traced activity
  5. Item
    Factory insurance
    Answer
    General overhead
  6. Item
    Maintenance
    Answer
    General overhead
  7. Item
    Utilities
    Answer
    General overhead
  8. Item
    Depreciation
    Answer
    General overhead
Right
General overhead
Instructions
Swipe left for an activity with its own rate, right for general factory overhead.
_Source: Jonick, Principles of Managerial Accounting, section 4.4 Activity-Based Costing for a Manufacturing Business_

Open this exercise →

How to practise

  1. Choose a Activity-Based Costing question and try to work out your answer.
  2. Open the question to check the correct answer and read its worked solution.
  3. Continue in the app for bite-sized lessons, explanations and review with Quill. You can start without creating an account.

More Management Accounting topics