A can do a piece of work in 25 days and B can do it in 20 days. They work together for 5 days and then A goes away. How many more days will B require to finish the work?
A9 days
B10 days
C11 days
D12 days
Answer & Solution
Correct answer: C. 11 days
A's one-day work is $1/25$ and B's is $1/20$. Together they do $1/25+1/20=9/100$ of the work per day, so in 5 days they complete $5\times 9/100=9/20$. The remaining work is $1-9/20=11/20$. Since B alone does $1/20$ per day, he needs $(11/20)\div(1/20)=11$ days.
Related questions
The study of inequalities is described as useful in solving problems in science and:A firm needing at least 6 units and at most 10 would write that as a:Which sign makes a statement an inequality rather than an equation?Unless stated otherwise, inequalities in that chapter are solved over the set of:The set of all values of the variable that make an inequality true is called its:Solving 4x plus 3 less than 6x plus 7 gives:When x is a real number in that inequality, the solution set is written as:When x is an integer in that inequality, the largest solution is: