At which location was the foundation stone for the NLC Talabira Thermal Power Project (3x800 MW) laid by the Prime Minister?

AKanpur Nagar (UP), 8 May 2018
BAnuppur (MP), 24 June 2024
CSundergarh (Odisha), 22 June 2024
DTareikela (Jharsuguda, Odisha), 3 February 2024
Answer & Solution
Correct answer: D. Tareikela (Jharsuguda, Odisha), 3 February 2024
The NLC Talabira Thermal Power Project (3x800 MW) is a pithead station at Tareikela, Jharsuguda District, Odisha. Foundation stone was laid by PM on February 3, 2024. Anticipated commissioning: Unit 1 Mar 2029, Unit 2 Sept 2029, Unit 3 Mar 2030. (Source: AR 2024-25 Ch 4 section 1.3.iv.)